Preston Road Bridge Demolition

WHAT TO EXPECT THIS WEEKEND:

Thursday night, November 15th: Switch northbound and southbound Preston Road traffic to the newly constructed half of the bridge.

Preston Road Bridge

 

Preston Bridge Demo Step 1

STEP 1: 9pm Nov 16th – Noon Nov 17th

  • Eastbound LBJ reduced down to 1 lane under Preston Road

  • The eastbound LBJ exit ramp to Hillcrest Road closed

Preston Road bridge closed.

 

Preston Bridge Demo Step 2

 STEP 2: Noon Nov 17th - 7pm Nov 17th

  • 2 right lanes closed on eastbound LBJ under Preston Road

  • The eastbound LBJ exit ramp to Hillcrest Road closed

Various lanes closed on Preston Road bridge.

 

Preston Bridge Demo Step 3

Step 3: 7pm Nov 17th – Noon Nov 18th

  • The westbound LBJ exit ramp to Montfort Drive closed

  • The westbound LBJ entrance ramp from Hillcrest Road closed

Preston Road bridge closed.

 

Preston Bridge Demo Step 4

Step 4: Noon Nov 18th – 8pm Nov 18th

  • 2 right lanes closed on westbound LBJ under Preston Road

  • The eastbound LBJ exit ramp to Hillcrest Road closed

  • Various lanes closed on Preston Road bridge

Various lanes closed on Preston Road bridge.

 

Preston Bridge Demo Step 5

Step 5: 8pm Nov 18th – 6am Nov 19th

Various lanes closed on eastbound and westbound LBJ under Preston Road

 

What’s Next for the LBJ Express Construction Over the DNT?

The LBJ Express Team has reduced lanes on LBJ Freeway over the Dallas North Tollway (DNT) and the first phase of demolition over the DNT has been completed, so what’s next?

The reconstruction of LBJ Freeway over the DNT will occur in 4-Phases:

PHASE 1:The first phase of the process has already been completed with the demolition of the outside lanes.

Demolition of LBJ Express bridges over the DNT

PHASE 2: The next phase is to reconstruct those outside, general purpose, lanes of LBJ Freeway, and the 6-step processof construction of the bridges over the DNT for the new outside lanes has already begun!

Phase 2: Westbound Reconstruction Area

Once the outside lanes have been entirely reconstructed, general purpose lane traffic will shift outward to those newly constructed bridges. At this point, the entrance and exit loops connecting LBJ Freeway and the DNT will be reconstructed and open. This will allow the through lanes of LBJ Freeway to be restored back to 4 lanes in each direction.

PHASE 3: The traffic shift to the exterior new bridges will allow space for the third phase of demolishing the inside current general purpose lanes of LBJ Freeway over the DNT to allow for Phase 4.

PHASE 4: The last phase will consist of constructing the middle, managed-toll, lanes over the DNT.

Future Highway at the DNT Intersection

Stay tuned for more updates on the LBJ Express over the Dallas North Tollway as construction progresses!